Wind study results and site selection
Navigant Consulting Inc completed the feasibility study for the wind energy project.
Main points from the Navigant Consulting Inc's wind study:
- The study found no fatal flaws that would exclude the entire South Farms area from the installation of one or more wind turbine-generators.
- Site D was identified as the best-fit location, located along Philo Road south of Curtis Road and north of Church Road.
- Power costs are estimated to be in the range of 3.5 cents/kWh to 6.2 cents/kWh (third party contributions can significantly lower these values).