  1. Labor & Employment Relations

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 179 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 29,829 hours. The simple payback for this project is 3.48 years.

  2. Board of Trustees approves Solar Farm

    Associated Project(s): 

    The Board of Trustees for the University of Illinois approved the purchase plans for the Solar Farm on Thursday.  The next steps are to complete the Development Agreement, Land-Lease Agreement, and Power Purchase Agreement.  Once these are completed, the Solar Farm vendor will begin the design and implementation of the Solar Farm at the southwest corner of Windsor Road and First Street.  The entire site should be completed and operational by the end of 2013.

  3. Atmospheric Sciences Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 221 T-12 fixtures in the Atmospheric Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 34,365 hours. The simple payback for this project is 3.83 years.

  4. Meat Sciences Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 367 T-12 fixtures in the Meat Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 66,103 hours. The simple payback for this project is 2.91 years.

  5. Horticulture Field Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 256 T-12 fixtures in the Horticulture Field Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,187 hours. The simple payback for this project is 3.58 years.

  6. SSC formal proposal submitted via email

    Associated Project(s): 

    Due to the Board of Trustees meeting schedule, the SSC has agreed to do a straw-poll about the funding of the Solar Farm project at their upcoming meeting on Oct. 26, 2012.  They requested a full proposal be submitted this week, for review by committee members this coming week.  The submitted proposal and associated calculations are attached here.

  7. Admin Info Tech Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.

  8. Art and Design Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,250 T-12 fixtures in the Art and Design Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 202,172 hours. The simple payback for this project is 3.47 years.