The solar PV design for the rooftop of the Idea Garden shed is 12 panels with 340 Watts each, which is a total of 4.08 kWdc. The construction estimate is in progress at F&S, then an interconnect agreement will be needed from Ameren.
Project Family
-
Solar Energy on Campus
- BIF Rooftop Solar PVs
- E37 Parking Lot Solar Lighting
- ECE Rooftop Solar PVs
- Ground Mounted Solar PVs BRC Research Test Bed
- Install Solar PVs on NCPD
- KCPA Rooftop Solar Feasibility Study
- Rooftop Solar Potential
- SSC Solar Feasibility Study
- Solar Farm 1.0
- Solar Farm 2.0
- Solar PVs at Idea Garden
- Solar PVs on Fruit Farm Admin Building
- Solar Panels on Everitt Lab
- Solar Thermal at ARC
- Speech and Hearing Rooftop Solar PVs
- Uni High Gym Rooftop Solar PVs
- Wassaja Hall Rooftop Solar PVs
Associated Collections
Description
Background
Project Team
-
Project Leader:
Ryan PankauTeam Members:
- Ava Heap
- Sandra Mason
- Andrew Stumpf
- Kristine Chalifoux
- Brad Kline
Dates
-
Proposed December 22, 2015Proposed by Ava HeapInvestigated February 1, 2016Investigated by Kristine ChalifouxApproved March 8, 2016Approved by Architecture Review Committee