Projects Updates for place: Swanlund Administration Building

  1. Illini Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 610 T-12 fixtures in Illini Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 96,185 hours. The simple payback for this project is 3.56 years.

  2. Huff Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 426 T-12 fixtures in Huff Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 67,172 hours. The simple payback for this project is 3.56 years.

  3. Harker Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 485 T-12 fixtures in Harker Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,475 hours. The simple payback for this project is 3.56 years.

  4. Harding Band Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 304 T-12 fixtures in the Harding Band Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 47,935 hours. The simple payback for this project is 3.81 years.

  5. Colonel Wolfe School

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 298 T-12 fixtures in the Colonel Wolfe School were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 46,989 hours. The simple payback for this project is 3.55 years.

  6. Civil Engineering Hydrosystems Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 402 T-12 fixtures in the Civil Engineering Hydrosystems Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 63,387 hours. The simple payback for this project is 3.13 years.

  7. Ceramics Kiln House

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.

  8. Architecture Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 618 T-12 fixtures in the Architecture Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 97,446 hours. The simple payback for this project is 3.47 years.

  9. Animal Sciences Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,724 T-12 fixtures in the Animal Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 271,840 hours. The simple payback for this project is 3.56 years.

  10. Uni High School

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 450 T-12 fixtures in Uni High School were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 70,895 hours. The simple payback for this project is 3.55 years.

  11. South Studio #6

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 189 T-12 fixtures in South Studio #6 were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 48,303 hours. The simple payback for this project is 1.76 years.

  12. Illini Union Bookstore

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 153 T-12 fixtures in the Illini Union Bookstore were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 24,077 hours. The simple payback for this project is 3.65 years.

  13. Education Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,416 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 327,869 hours. The simple payback for this project is 1.12 years.

  14. Imported Swine Research Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 323 T-12 fixtures in the Imported Swine Research Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 50,918 hours. The simple payback for this project is 3.56 years.

  15. Labor & Employment Relations

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 179 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 29,829 hours. The simple payback for this project is 3.48 years.

  16. Atmospheric Sciences Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 221 T-12 fixtures in the Atmospheric Sciences Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 34,365 hours. The simple payback for this project is 3.83 years.

  17. Meat Sciences Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 367 T-12 fixtures in the Meat Sciences Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 66,103 hours. The simple payback for this project is 2.91 years.

  18. Horticulture Field Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 256 T-12 fixtures in the Horticulture Field Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 40,187 hours. The simple payback for this project is 3.58 years.

  19. Admin Info Tech Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.