  1. Turner Student Services Building

    Associated Project(s): 

    A total of 3,799 lighting fixtures in the National Soybean Research Center were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 597,686 hours. The Simple Payback for changing the fixtures in the Turner Student Services Building is 1.89 years.

  2. Psychology Building

    Associated Project(s): 

    The lighting fixtures in the Psychology Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. In this facility, 2,571 fixtures were changed. This will allow an Annual kWh Savings of 393,534 hours. The L.S. project seperately funded 1,812 of the 2,571 fixtures. Occupancy sensors were also installed in the lighting retrofit of this building in order to provide further energy savings.

  3. National Soybean Reasearch Center

    Associated Project(s): 

    The 1,481 lighting fixtures in the National Soybean Research Center were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. This will allow an Annual kWh Savings of 248,885 hours. The Simple Payback for changing the fixtures in the National Soybean Research Center is 1.28 years.

  4. English Building

    Associated Project(s): 

    The lighting fixtures in the English Building were changed from T-12 fixtures to T-8 fixtures as part of the ICECF Lighting Retrofit. In this facility, 1,006 fixtures were changed. This will allow an Annual kWh Savings of 245,319 hours. The Simple Payback for changing the fixtures in the English Building is 1.31 years. Occupancy sensors were also installed in the lighting retrofit of this building in order to provide further energy savings.

  5. LED Exit Signs Phase 2

    Associated Project(s): 

    Phase 2 of the LED Exit Sign project to replace incandescent exit signage with LED fixtures started on June 30, 2008. This phase of the project will replace fixtures in the Armory, Foellinger Auditorium, Harding Band Building, Illini Hall, the Optical Physics Building, the Illinois Program for Research & Humanities, the Architecture Building, Noble Hall, the Art & Design Building, the Music Building, Flagg Hall, and University High School.

  6. LED Exit Signs Phase 1

    Associated Project(s): 

    Phase 1 of the LED Exit Sign project will replace incandescent exit signage with LED fixtures in facilities used for the Engineering Open House. The building involved are the Material Sciences and Engineering Building,  the Mechanical Engineering Building, the Transportation Building, Altgeld Hall, Morrill Hall, Burrill Hall, Noyes Laboratory, and the Undergraduate Library.