Project History
-
9/5/2018
-
9/5/2018
Facilities & Services Waste Management handles trash and recycling pick-up for the majority of campus facilities. The exterior garbage and recycling dumpsters are emptied on a regular schedule, by campus drivers working for the Waste Transfer
Project Family
Description
Background
Funding Sources
Funding Source | Total Amount Approved | Total Amount Spent |
---|---|---|
$560.00 | $0.00 | |
Totals | $560.00 | $0.00 |
Project Team
-
Project Leader:
Pete VarneyTeam Members:
- Morgan White
- Shawn Patterson
- Shantanu Pai
Dates
-
Proposed November 14, 2014Proposed by Shantanu PaiApproved December 12, 2014Approved by Tracy OsbyStarted September 12, 2018Started by Pete Varney