  1. EGen003 PPA term recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on March 30th, 2016, to discuss the recommendation EGen003 PPA Term and started the assessment. iWG's official recommendation was:

    "We understand that the University is currently advocating for state legislative relief from a number of procurement-related restrictions, and we recommend that the University include in this effort a request to eliminate the 10-year limit on Power Purchase Agreements. If successful, this would allow (but not require) our campus and Prairieland Energy, Inc. to enter into long-term Power Purchase Agreements for renewable energy (including electricity and other renewable fuels) which may offer more favorable terms, perhaps even being less expensive than traditional energy options."

    See the attached file for the complete assessment of this recommendation with comments from all the iWG members.

    See SWATeam recommendation EGen003 PPA Term here.

  2. EGen003 PPA term recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "Take steps to allow a Power Purchase Agreement for electricity without any restriction on the term of the agreement."

    See attached the SWATeam recommendation EGen003 PPA term complete with comments from all the eGen SWATeam members.

    Attached Files: 
  3. EGen004 Electrification Study recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "Hire a consultant to undertake a study of electrifying most space and water heating on campus."

    See attached the SWATeam recommendation EGen004 Electrification Study complete with comments from all the eGen SWATeam members.

  4. EGen002 Utilities Master Plan Review recommendation - Unit response - Denied

    Facilities & Services unit rejected the recommendation. F&S's response was sent to the iWG and EGen SWATeam on June 15th, 2015. However, this recommendation led to the EGen004 Electrification Study recommendation.

    See SWATeam recommendation EGen004 Electrification Study here.

    See Transmittal of EGen002 Utilities Master Plan Review to the unit here.

    See iWG Assessment of EGen002 Utilities Master Plan Review here.

    See SWATeam recommendation EGen002 Utilities Master Plan Review here.

  5. EGen002 Utilities Master Plan Review recommendation - Transmittal

    Following the completion of iWG Assessment, the recommendation was forwarded to the Facilities & Services unit on May 29th, 2015.

    See iWG Assessment of EGen002 Utilities Master Plan Review here.

    See SWATeam recommendation EGen002 Utilities Master Plan Review here.

  6. EGen002 Utilities Master Plan Review recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on May 21st, 2015, to discuss the EGen002 Utilities Master Plan Review recommendation, and started the recommendation. Their official comment on this recommendation was:

    "We recommend that the Utilities Master Plan be vetted by outside experts with specific expertise in renewable energy and geothermal heat pump technology."

    See the attached file for the complete iWG Assessment with comments from all the iWG members.

    See SWATeam recommendation EGen002 Utilities Master Plan Review here.

  7. EGen002 Utilities Master Plan Review recommendation - Submitted

    The eGen SWATeam submitted a recommendation to the iWG stating, "Seek expert external reviews of the Utilities Master Plan."

    See attached the SWATeam recommendation EGen002 Utilities Master Plan Review complete with comments from all the eGen SWATeam members.

  8. EGen001 Wind PPA recommendation - Assessment with all comments

    The iCAP Working Group (iWG) met on August 28th, 2014, to discuss the EGen001 Wind PPA recommendation, and they started the assessment for this recommendation. 

    See the attached file for complete assessment with comments from all the iWG members.

    See SWATeam recommendation EGen001 Wind PPA here.

  9. EGen001 Wind PPA recommendation - Transmittal to the unit

    The SWATeam recommendation complete with the iWG Assessment with comments from all the iWG members was transmitted to the Facilities & Services on August 28th, 2014.

    For any future updates on this item, please visit the Wind Power Purchase Agreement (PPA) project.

    See iWG Assessment for EGen001 Wind PPA here.

    See SWATeam recommendation EGen001 Wind PPA here.

  10. EGen001 Wind PPA recommendation - Submittal

    The eGen SWATeam submitted a recommendation to the iWG stating, "We strongly endorse pursuing Power Purchase Agreements (PPAs) with one or more Wind Farms as soon as possible. Given current market conditions, we believe that a PPA with one or more Wind Farms presents a great opportunity to purchase renewable energy in support of the campus iCAP targets."

    See attached the SWATeam recommendation EGen001 Wind PPA complete with comments from all the eGen SWATeam members.