August 2014 minutes
See attached minutes from the iCAP Working Group.
See attached minutes from the iCAP Working Group.
The iCAP Working Group (iWG) met on August 28th, 2014, to discuss the EGen001 Wind PPA recommendation, and they started the assessment for this recommendation.
See the attached file for complete assessment with comments from all the iWG members.
See SWATeam recommendation EGen001 Wind PPA here.
The SWATeam recommendation complete with the iWG Assessment with comments from all the iWG members was transmitted to the Facilities & Services on August 28th, 2014.
For any future updates on this item, please visit the Wind Power Purchase Agreement (PPA) project.
See iWG Assessment for EGen001 Wind PPA here.
See SWATeam recommendation EGen001 Wind PPA here.
Prairieland Energy Inc (PEI) provided the attached schedule for the Request for Information (RFI) and the potential Request for Proposals (RFP) for a Power Purchase Agreement (PPA).
On July 29, the iCAP Working Group (iWG) met for the first time. Read more about that first meeting in the attached minutes.
The eGen SWATeam submitted a recommendation to the iWG stating, "We strongly endorse pursuing Power Purchase Agreements (PPAs) with one or more Wind Farms as soon as possible. Given current market conditions, we believe that a PPA with one or more Wind Farms presents a great opportunity to purchase renewable energy in support of the campus iCAP targets."
See attached the SWATeam recommendation EGen001 Wind PPA complete with comments from all the eGen SWATeam members.
Evan:
We contacted UA. They're supposed to give us a RFP schedule next week. That should give us a better idea of the timeline.
-Al Stratman
From: Evan DeLucia [mailto:delucia@life.illinois.edu]
Sent: Thursday, May 29, 2014 5:39 PM
To: McCall, Benjamin
Cc: Stratman, Allan
Subject: SWAT report on energy generation
Ben,
In the absence of a fully formulated SWAT process - iWG and the Sustainability Council have yet to be formed - I forwarded the May 2014 position paper from the 'energy generation' team directly to Al Stratman for consideration.
Under the SWAT process, the teams should be... "developing and recommending specific actions or initiatives the campus should under take to meet iCAP targets..." The energy generation SWAT did a nice job of recommending a specific action that would help meet our targets.
To paraphrase, Al responded...
I've taken the liberty of copying Al to be sure I didn't misrepresent his response to me.
Al, do you have any idea of what might be a reasonable time frame would be for completing an analysis of the feasibility, costs, and benefits of purchasing wind power for campus?
Cheers,
Evan
Here is the first recommendation from the Energy Generation SWATeam.
"We strongly endorse obtaining Power Purchase Agreements (PPAs) with one or more Wind Farms as soon as possible. It is unlikely that a better opportunity to purchase renewable energy will present itself in the foreseeable future."