Projects Updates for place: Snyder Hall

  1. Email to students about CCN

    Associated Project(s): 

    From: Foote, Gerard Paul
    Sent: Monday, December 02, 2013 1:19 PM
    To: Mondello, Jessica Rae; Ross, Karoline Jeanne; Myles, Kirsten N; Khan, Nadia; Jones, KeJuan M; Jamal, Sahir S; Anjum, Hiba Sattar; Sheth, Saloni B
    Cc: Johnston, Morgan B; Hochman, Sarah E; Hauger, Kevin J
    Subject: Campus Conservation Nationals Introduction email

    Hello everyone,

    I hope everyone had a great holiday!

    As a follow-up to our initial meeting, I would like to thank you all for your interest in participating in the first ever UIUC CCN competition.

    It is great to find fellow students interested in making a difference in the world, and sustainability in energy conservation is a great place to start.

    This competition is promising to be an Awesome experience!

    Getting started: I would like to schedule a meeting where we discuss the roles needed and create the competition schedule.

    I know these next two weeks are demanding but we need to meet,

    With this in mind;  I  am available most evenings after 5 pm,  Mon and Tue I have prior arrangements but can cancel them if needed.

    Please respond today or Tue with which evenings and times that work or don’t work for you, then I will post the meeting options that meet the majority

    Attached is a sample timeline. Keep  in mind these are recommendations and we may opt to re-arrange to best fit our team’s needs.

    When I met with you there was some question as to the duties in each role participating in the competition, attached is a pdf of sample team position descriptions.

    When responding with meeting times if you already know what role or roles you are interested in please indicate that in your response.  Thank you!

    http://competetoreduce.org/ccn/plan.html This is a link to the competition training webinars, I encourage you to scroll to the bottom and read the CCN Competition Planning Guide and the CCN Data Collection & BuildingOS Guide. These will provide important data for understanding what and how we are going to accomplish CCN, as the competition organization team.

    For those of you that are more ambitious watch the webinars as they are well prepared and explain many facets of the competition in great detail.

    I have downloaded and watched them all!  

    As for an update on the current status of the competition;

    -We have a tentative timeline for collection and competition weeks, however we have been invited to participate in a Big 10 version of the competition as well, this may require us to modify our schedule to match the Big 10 timeline, will update as we progress.

    -The 20 res Halls with metering capability have been identified and I am working with the metering dept. to get training on how to digitally collect this data.

    -Most of the signatures on the CCN registration have been received with 2 remaining this will be completed by Dec 15th 2013.

    Thank you again for your participation and I look forward to working with all of you in creating this Amazing competition at the University of Illinois Urbana Champaign.

    Paul Foote

     

  2. note about getting students involved

    Associated Project(s): 

    -Involving the individual colleges for spreading the word to gain student leaders and volunteers, ex: College of Environmental Sciences, Atmospheric Sciences, ACES etc… ?

    After gaining their support, I would send a mass e-mail to the admins office and they could forward to students

  3. FARH Food Service

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 453 T-12 fixtures in FARH Residence Hall's Food Service Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 71,429  hours. The simple payback for this project is 2.81 years.

  4. FARH Oglesby Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 126 T-12 fixtures in FARH Oglesby Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 19,868  hours. The simple payback for this project is 2.81 years.

  5. FARH Trelease Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 110 T-12 fixtures in FARH Trelease Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,345  hours. The simple payback for this project is 2.81 years.

  6. Sherman Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 51 T-12 fixtures in Sherman Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,042  hours. The simple payback for this project is 2.81 years.

  7. ISR Food Service

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 381 T-12 fixtures in ISR Residence Hall Food Service Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 60,076  hours. The simple payback for this project is 2.81 years.

  8. ISR Lounge

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 176 T-12 fixtures in ISR Residence Hall Lounge were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 27,752  hours. The simple payback for this project is 2.81 years.

  9. ISR Townsend

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 791 T-12 fixtures in ISR Townsend Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 124,725  hours. The simple payback for this project is 2.81 years.

  10. ISR Wardall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 73 T-12 fixtures in ISR Wardall Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 11,511  hours. The simple payback for this project is 2.81 years.

  11. Student Staff Apartments #2

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 100 T-12 fixtures in the Student Staff Apartments #2 were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 15,768  hours. The simple payback for this project is 2.81 years.

  12. Student Staff Apartments

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 136 T-12 fixtures in the Student Staff Apartments were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 21,444  hours. The simple payback for this project is 2.81 years.

  13. Evans Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 500 T-12 fixtures in Evans Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 78,840  hours. The simple payback for this project is 2.81 years.

  14. Busey Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 391 T-12 fixtures in Busey Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 61,653 hours. The simple payback for this project is 2.81 years.

  15. Taft Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 111 T-12 fixtures in Taft Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,502  hours. The simple payback for this project is 2.81 years.

  16. Van Doren Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 41 T-12 fixtures in Van Doren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 6,465  hours. The simple payback for this project is 2.81 years.

  17. Barton Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 53 T-12 fixtures in Barton Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 8,357  hours. The simple payback for this project is 2.81 years.

  18. Clark Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 110 T-12 fixtures in Clark Residence Hall Administration Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 17,345  hours. The simple payback for this project is 2.81 years.

  19. Lundgren Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 59 T-12 fixtures in Lundgren Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 9,303  hours. The simple payback for this project is 2.81 years.

  20. Hopkins Hall

    Associated Project(s): 

    As part of the Housing Lighting Retrofit, 153 T-12 fixtures in Hopkins Residence Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 24,125  hours. The simple payback for this project is 2.81 years.