You are here

Projects Updates for place: International Studies Building

  1. Printing and Photographic Services Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 862 T-12 fixtures in the Printing and Photographic Services Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 151,916 hours. The simple payback for this project is 3.15 years.

  2. Agriculture Bioprocess Lab

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 436 T-12 fixtures in the Agriculture Bioprocess Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,289 hours. The simple payback for this project is 3.62 years.

  3. Animal Sciences A/C Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 50 T-12 fixtures in the Animal Sciences A/C Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 7,884  hours. The simple payback for this project is 3.56 years.

  4. University Press

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 488 T-12 fixtures in the University Press Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,948 hours. The simple payback for this project is 3.64 years.

  5. Transportation Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 547 T-12 fixtures in the Transportation Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 86,251 hours. The simple payback for this project is 3.56 years.

  6. Temple Hoyne Buell Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 471 T-12 fixtures in Temple Hoyne Buell Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,267 hours. The simple payback for this project is 3.56 years.

  7. Speech and Hearing Clinic

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 47- T-12 fixtures in the Speech and Hearing Clinic were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 74,110 hours. The simple payback for this project is 3.08 years.

  8. Shelford Vivarium Greenhouse

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 335 T-12 fixtures in the Shelford Vivarium Greenhouse were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 52,823 hours. The simple payback for this project is 3.53 years.

  9. Personnel Services Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 433 T-12 fixtures in the Personnel Services Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 68,275 hours. The simple payback for this project is 3.2 years.

  10. Nuclear Physics Lab

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 415 T-12 fixtures in the Nuclear Physics Lab were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 65,437 hours. The simple payback for this project is 3.56 years.

  11. Natural Resources Studies Annex

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 1,200 T-12 fixtures in the Natural Resources Studies Annex were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 189,216 hours. The simple payback for this project is 3.56 years.

  12. Levis Faculty Center

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 189 T-12 fixtures in the Levis Faculty Center were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 29,802 hours. The simple payback for this project is 3.56 years.

  13. International Studies Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 571 T-12 fixtures in the International Studies Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 90,035 hours. The simple payback for this project is 3.56 years.

  14. Illini Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 610 T-12 fixtures in Illini Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 96,185 hours. The simple payback for this project is 3.56 years.

  15. Huff Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 426 T-12 fixtures in Huff Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 67,172 hours. The simple payback for this project is 3.56 years.

  16. Harker Hall

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 485 T-12 fixtures in Harker Hall were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 76,475 hours. The simple payback for this project is 3.56 years.

  17. Harding Band Building

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 304 T-12 fixtures in the Harding Band Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 47,935 hours. The simple payback for this project is 3.81 years.

  18. Colonel Wolfe School

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 298 T-12 fixtures in the Colonel Wolfe School were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 46,989 hours. The simple payback for this project is 3.55 years.

  19. Civil Engineering Hydrosystems Laboratory

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 402 T-12 fixtures in the Civil Engineering Hydrosystems Laboratory were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 63,387 hours. The simple payback for this project is 3.13 years.

  20. Ceramics Kiln House

    Associated Project(s): 

    As part of the Lighting Retrofit #5, 687 T-12 fixtures in the Admin Tech Info Building were replaced with more energy-efficient T-8 fixtures. This switch will incur an Annual kWh Savings of 112,316 hours. The simple payback for this project is 3.42 years.