You are here
- Home
- Building removal
Building removal
Posted by Morgan White on June 17, 2013
There are three buildings on the site of the future Solar Farm. The SSC requested that the Timber Frame barn be salvaged, rather than demolished. The company that is the preferred vendor for this work provided this detail:
It would be our intention to reuse 100% of the wood components. We would re-erect the building as it stands with only modifications being to the interior layout spacing. We will recycle the steel roofing. We would handle the concrete in non-landfill manner; planned use is as a fencing fill for the new owner. Battens and doors and any exterior wood treatments would be reused in the re-newed structure. Although the nails will not be reused in the re-erection of the building, they have been allocated to go to a local BFA candidate.