You are here
- Home
- Estimates from GE proposal
Estimates from GE proposal
Posted by Sarthak Prasad on September 17, 2007
The project proposal was received from GE Wind Energy on September 10th 2007, and opened on September 16th 2007. According to the proposal, the estimate for construction is a range of $11.4 million to $12.6 million and for the total project budget would be $12.1 million to $13.4 million.
Also, GE Wind Energy proposal stated an October 1, 2007 expiration date! This estimate infers that the university's current budget ($5.7 million) is enough to build only one turbine.